On Our Project, We're Always 90% Done

Although I love reading programming books, I find software project management books to be some of the most mind-numbingly boring reading I've ever attempted. I suppose this means I probably shouldn't be a project manager. The bad news for the Stack Overflow team is that I effectively am one.

That's not to say that all software project management books are crap. Just most of them. One of the few that I've found compelling enough to finish is Johanna Rothman's Behind Closed Doors: Secrets of Great Management. She co-wrote it with Esther Derby.

Behind Closed Doors: Secrets of Great Management

After reading it, you'll realize this is the book they should be handing out to every newly minted software project manager. And you'll be deeply depressed because you don't work with any software project managers who apparently have read it.

I originally discovered Johanna when one of her pieces was cited in the original Spolsky Best Software Writing book. Her article on team compensation (pdf) basically blew my mind; it forced me to rethink my entire perspective on being paid to work at a job. You should read it. If you have a manager, you should get him or her to read it, too. (Update: this essay is actually by Mary Poppendieck, who is also great. I'm leaving it in the post because it's fantastic reading, even if it's a little off topic.)

Since then, I've touched on her work briefly in Schedule Games and You Are Not Your Job. But I'd like to focus on a specific aspect of project management that I'm apparently not very good at. A caller in Podcast #16 took me to task for my original Stack Overflow schedule claims way back in late April. What was supposed to be "6 to 8 weeks" became.. well, something more like three months.

My problem is that I'm almost pathologically bad about writing things down. Unless I'm writing a blog entry, I suppose. I prefer to keep track of what I'm doing in my head, only anticipating as far ahead as the next item I plan to work on, while proceeding forward as quickly as I can. I think I fell prey, at least a little bit, to this scenario:

"Look, Mike," Tomas said. "I can hand off my code today and call it 'feature complete', but I've probably got three weeks of cleanup work to do once I hand it off." Mike asked what Tomas meant by "cleanup." "I haven't gotten the company logo to show up on every page, and I haven't gotten the agent's name and phone number to print on the bottom of every page. It's little stuff like that. All of the important stuff works fine. I'm 99-percent done."

Do you see the problem here? I know, there are so many it's difficult to know where to begin listing them all, but what's the deepest, most fundamental problem at work here?

This software developer does not have a detailed list of all the things he needs to do. Which means, despite adamantly claiming that he is 99 percent done -- he has no idea how long development will take! There's simply no factual basis for any of his schedule claims.

It is the job of a good software project manager to recognize the tell-tale symptoms of this classic mistake and address them head on before they derail the project. How? By forcingencouraging developers to create a detailed list of everything they need to do. And then breaking that list down into subitems. And then adding all the subitems they inevitably forgot because they didn't think that far ahead. Once you have all those items on a list, then -- and only then -- you can begin to estimate how long the work will take.

Until you've got at least the beginnings of a task list, any concept of scheduling is utter fantasy. A very pleasant fantasy, to be sure, but the real world can be extremely unforgiving to such dreams.

Johanna Rothman makes the same point in a recent email newsletter, and offers specific actions you can take to avoid being stuck 90% done:

  1. List everything you need to do to finish the big chunk of work. I include any infrastructure work such as setting up branches in the source control system.

  2. Estimate each item on that list. This initial estimate will help you see how long it might take to complete the entire task.

  3. Now, look to see how long each item on that list will take to finish. If you have a task longer than one day, break that task into smaller pieces. Breaking larger tasks into these inch-pebbles is critical for escaping the 90% Done syndrome.

  4. Determine a way to show visible status to anyone who's interested. If you're the person doing the work, what would you have to do to show your status to your manager? If you're the manager, what do you need to see? You might need to see lists of test cases or a demo or something else that shows you visible progress.

  5. Since you've got one-day or smaller tasks, you can track your progress daily. I like to keep a chart or list of the tasks, my initial estimated end time and the actual end time for each task. This is especially important for you managers, so you can see if the person is being interrupted and therefore is multitasking. (See the article about the Split Focus schedule game.)

I'm not big on scheduling -- or lists -- but without the latter, I cannot have the former. It's like trying to defy the law of gravity. Thus, on our project, we're always 90% done. If you'd like escape the 90% done ghetto on your software project, don't learn this the hard way, like I did. Every time someone asks you what your schedule is, you should be able to point to a list of everything you need to do. And if you can't -- the first item on your task list should be to create that list.

Posted by Jeff Atwood    View blog reactions
« Quantity Always Trumps Quality
Music to (Not) Code By »
Comments

Hmmm....I'm surprised you didn't link to

http://www.joelonsoftware.com/articles/fog0000000245.html
http://www.joelonsoftware.com/items/2007/10/26.html

given that they say many of the same things.

Karellen on August 5, 2008 5:10 AM

Huh? The article you cite in paragraph 4 was written by Mary Poppendieck, not Johanna Rothman...

Paul Sligar on August 5, 2008 5:11 AM

On a related subject: You can improve your estimates by using 3-point-estimates (Warning: takes about 20 minutes to read):

http://www.visionarytools.com/decision-making/3-point-estimating.htm

But one estimate per task is of course still better than no estimate per task or (even worse) no list of tasks :)

Daniel Lehmann on August 5, 2008 5:14 AM

Or maybe to Steve McConnell:

http://blogs.construx.com/blogs/stevemcc/archive/2007/09/23/building-a-fort-lessons-in-software-estimation.aspx

This problem seems to be a really tough software development nut to crack. I wonder what it is about software developers (or our managers) that makes us so prone to being "90% done"?

Brian on August 5, 2008 5:14 AM

The other problem is analysis paralysis. So busy trying to make decisions that you never make any. Sometimes it is best to just get on with stuff and then use your understanding of the problem to do the estimate properly.

Jeff - have you looked at any of the Anti-patterns stuff? I read the book years ago and it made sense then, main thrust was to identify what kind of problem you suffer from and how to fix it. Worth a look.

Francis Fish on August 5, 2008 5:31 AM

> I wonder what it is about software developers (or our managers) that makes us so prone to being "90% done"?

I chalk it up to the desire to please, both ourselves and our managers. The way I see it, this will persist so long as the boss is more excited to hear "it's 90% done" than she is to hear "I've detailed the task and I estimate I'm really only 25% done." The later means your deadline is going to slip, and that's a reality that a lot of people will resist.

It's surely more immediately satisfying to convince yourself you're 90% done than face the reality of the situation. I think for most people, getting past that rush will require having a manager that's honestly appreciative of being presented reality, and displeased when presented a fantasy.

Brian Boss on August 5, 2008 5:33 AM

Create a list of tasks? You must be joking. I've got all this real work to do. ;)

Ciaran on August 5, 2008 5:40 AM

"How's that list coming?"

"it's 90% done... just the little things I haven't thought of and don't know about remain."

SteveC on August 5, 2008 5:49 AM

Have to agree. I only ever track tasks at 0% or 100% complete.

If anything more fine-grain is needed then the task can be broken down further.

Scott on August 5, 2008 5:49 AM

The Modified Pareto rule for software projects:

When you are 80% done, you will spend 80% of the time used up until this point, on the remaining 20%.

This is a recursive rule, so you will actually never be done - although you probably will get to a point where you consider yourself close enough to done to actually ship.

Lars Fosdal on August 5, 2008 5:58 AM

Trouble is, you have to maintain the list, adding on all the things that you didn't think you hadn't thought of.

It might well be that new stuff comes up, that has to be added. I find it has a tendency to add about 10% to the overall estimate.

One day, I'll get myself and my users well-enough organised to be able to use stories and iterations (like XP) or sprints (Scrum) or something similar.

One day.

Mike Woodhouse on August 5, 2008 6:08 AM

Another practical project management book is Simply Brilliant by Fergus O'Connell. Well worth the read - and it's an easy read too.

Neil Watson on August 5, 2008 6:12 AM

Yeah, let's map out all the features and break each feature down into tasks. Whack that into a plan and what do we have? Waterfall!

The real problem is that software development quite often involves invention. As Cockburn puts it: "A cooperative game of communication and invention."

Often, the only way we know everything we need to do is to actually do it.

Andrew Peters on August 5, 2008 6:15 AM

Not wishing to label everyone the same way, I think the dislike of lists and scheduling is fairly usual with software developers.

This might just be down to the idea of "If I could write down everything it needed to do then I'd have done it already!"

The advantage of Software as a Service is that a 90% complete solution can often be put live with the last 10% being "mopped up" as required.

This ties in well with a developers dislike of lists as the 90% list is a lot easier to produce. Ask for a list of everything needed to be done in order to go live and everything needed to be done to be complete and one will happen a lot quicker than the other.

As long as everyone at all stages is well prepared for this 90% mentality then it's actually a good morale and performance boost. It usually falls into the "possible" side of things rather than the "impossible".

Then when it comes to hitting the final 10% as a separate entity it also now falls into the "possible" side of things.

It's a Divide and Conquer mechanism for software development that I've always found extremely productive and nice to work with!

Robin Day
http://www.advorto.com

Robin Day on August 5, 2008 6:15 AM

If you do want to create a list, make sure you know what 'done' means for each item. If not, your list is just as useless as not having such such list. Worse, you've tricked yourself that you have such a list.

I am really tired of seeing such useless list from project managers ...

- Requirement
- Analysis
- Design
- Implementation/Programming
- Testing
- Release

Harry on August 5, 2008 6:16 AM

I find one way to have a better idea of how finished I am is to try to completely finish a task before I move on to the next one (or finish it as much as I can before I need to wait for something). I remember feeling blind panic when I was working on something once and I'd done all the major work but none of finishing up and had no idea where I was in relation to the Gantt chart I'd drawn up with my manager at the beginning.

Helen on August 5, 2008 6:22 AM

lists are good but they suffer the same flaw as memory - you can forget to put something on there. :)

i'm surprised this (making a list) is considered anything more than common sense to be frank. if someone has to be told this, they probably lack the natural aptitude to manage a project... still, i guess we must respect the training courses etc... its the way of the world.

although i will say the biggest project i work on with a list of objectives has slipped and slipped and slipped due to my failure to anticipate how much programming i am really going to do in my spare time.

moral: bad programmers can still run late with good lists. :)

jheriko on August 5, 2008 6:33 AM

I started having the same problem in my side-project - we were concnentrating on the big items, forgetting about the smaller ones. I've tried writing things down, and after 2 months of trying we ended up on trac integrated with our source control subversion.

Very nice way to go, you can add things to be done in a flash, from anywhere, so that you don't forget them.

Jakub Anderwald on August 5, 2008 6:46 AM

Yep, a list of task or to-do list really helps me do my work and know how far I am from finishing. I keep it on paper for now and always add items as I find out about them.

It's a good incentive to keep on working too when you see the list getting smaller and smaller.

Michel Billard on August 5, 2008 7:02 AM

Having a list is excellent, but you have to make sure your team understands that you cannot check off a single item until it is truly done.

Not code complete, not done but still needs tests, or done but needs refactoring. Not done means you delivered zero business value and thus you cannot show any progress (doing so would be lying). If you show the illusion of progress then you aren't painting the right picture to your stakeholders.

It's amazing how many programmers consider something done and then still work on it for hours (or days) longer to polish it.

Ben Scheirman on August 5, 2008 7:02 AM

The Poppendiecks should be more widely read.

This post resonates with me. I keep trying to use paper more to both block diagram and make lists before I fire up VS. I also try to write tests before the real code, but that doesn't always work.

I usually think about a solution before I implement it, but once I've split it up a little I think it's easy enough to just jump into the code. Then I wonder why it takes longer than I thought.

John Ferguson on August 5, 2008 7:06 AM

i'm 90% done reading this blog.

jin on August 5, 2008 7:10 AM

I just finished reading Time Management for System Administrators

http://www.thecrumb.com/2008/07/18/book-review-time-management-for-system-administrators/

And he had one good mantra: List the Work. Work the List.

I'm trying to use my bug tracker and Outlook tasks more and it's helping. Now I need to start busting those up into more sizable chunks...

Jim Priest on August 5, 2008 7:15 AM

Well done, Jeff.

I'm glad you owned up to your project management blooper. While I agree with Joel that this project's slippage is not a major issue in this case, the average developer is often faced with projects where schedule slips are disastrous. Thanks for setting a good example to all the "shoot-from-the-hip" estimators.

I think many a developer's pain in this area comes from being poorly managed. They are asked for a "rough estimate" on how long it would take to do x. They provide an overly optimistic estimate, and the project is approved on that basis. If they develop a realistic schedule and present it at this point, they are often harshly criticised for their inaccurate rough estimate, and the criticism continues through to the inevitably late delivery. If there is no schedule, however, the developer can continue to claim that he is 90% finished, and defend any "unforeseen problems" that may occur.

I have learned that the only way to counteract this pattern is to refuse to be drawn into giving a "rough estimate" for anything, and always asking for a complete requirements spec, whereupon I make the schedule and give the schedule as the estimate.

Keep on blogging, young Jedi.

Bork Blatt on August 5, 2008 7:28 AM

Semi-OT: For someone who likes it BIG and ROUND, your yellow-boxed ad at the bottom of your posts aren't very clickable...

http://twitter.com/codinghorror/statuses/876657644

Matt S on August 5, 2008 7:28 AM

Don't forget to include a line item in your time estimate for BSaP.


That's B.S. and Politics. All of the things that suck up your time, but have nothing to do with actually producing the end product. Meetings, convincing execs that the tool they heard about in some tech journal may not be the best thing for this project, etc.

Grant on August 5, 2008 7:32 AM

Sorry for implying the Poppendiecks should read more. I meant their work should be read by more people.

John Ferguson on August 5, 2008 7:35 AM

Ha. I work at Nucor (referenced in the Poppendieck article). Its a great place to work for the most part. There are problems with the incentive system, but its far better than the alternatives. Basically what Nucor has done is get all of its people focused on making more money for the company. If the company makes more money, we (the employees) all make more money. Its clear how to make more money ... produce more steel! Its not a principle that would be easily applied elsewhere.

TimC on August 5, 2008 7:51 AM

I agree, this is the only way to have accurate estimates and prevent the 90% done. I believe she wrote an article a few years ago and coined the term "inch pebbles" for these tasks.

And once you get your estimate, you still need to factor in the unknowable unknowns that pop up as you code.

Jeff Schwandt on August 5, 2008 7:57 AM

Jeff,

You're one awesome dude!

I listened to the podcast where that caller called you out for being behind schedule. I listened to Joel being the prick he sometimes is when he teaches others. Although I agreed with both of them, you should have kept track of your tasks, I don't think they taught the principle effectively. In spite of them, however, you had the guts to recognize your mistakes. I wish you success in trying to correct them.

Esteban on August 5, 2008 7:58 AM

I'd like to see a success story of this system being used on a real project.

Jonathan M on August 5, 2008 8:06 AM

I surprised people gripe about the delays. Anyone who has ever worked in software should know that delays are practically a way of life.

List or no list, software is still a tricky beast!

(Yes, you can minimize them, but come on!!! they still happen!!)

Keep up the hard work Jeff. I'm excited to see the site whenever it's ready.

Ben on August 5, 2008 8:17 AM

I think that the problem with all the project management is that you'll be stuck at 0% for a long time trying to map out everything, which could have been spent doing a POC or base implementation and which in the end will give you a better idea of the actual requirements. Oh, i'm 100% done i already have the requirements and implementation plan, and then BAM you encounter the issues that only come up in development and have to replan again.

Not defending all action and no planning, just that alot of planning will kill a project.

BTW, i think this post of yours is actually in conflict with the previous one.

Bobby on August 5, 2008 8:44 AM

@Karellen

I don't know if you noticed, but on the first article you linked to, it specifically says that it is outdated, and no longer valid, and specifically says not to read it.

Eric Kibbee on August 5, 2008 8:53 AM

this is also one of the cardinal rules of GTD, without a to-do list you can't finish anything, software development is not an exception.

JT on August 5, 2008 9:13 AM

I found "Software Estimation, demystifying the black art" a good read for this topic. Although by definition boring to practitioners, Steve McConnell's emphasis on empirical data points and the avoidance of guesstimation makes the content far more applicable than similar textbooks I've come across.

Casper Bang on August 5, 2008 9:17 AM

My lists tend to have a status entry for each actionable item (ie my actual assignments, rather than individual tasks that lead to the assignment being complete). In my current position, the status reads as follows:
DEV
Peer Review
TEST
User Acceptance Testing

and then if it passes all of those steps, I label it Production and move it to a different list, where I can pull back the details and notes I took on that particular item if something slips past testing. I also keep a list of every file I change while I'm working on that item, because I don't want to forget to check some little change to one file into source control and then spend more time looking for it later when it won't pass test or peer review.

Vizeroth on August 5, 2008 9:30 AM

Yes, I did notice.

But, I think that the first has a few interesting ideas that aren't in the second. It seems more targetted towards individual developers - it tells you how you can manage your own time and come up with your own estimates more accurately than before, all with a _really simple_ spreadsheet.

The second, evidence-based scheduling article seems to be more targetted towards project managers who oversee a number of developers, are far enough away from the estimates to do meta-analyses and such like, and have the time and incentives to create the interesting graphs and velocity measurements. I think a lot of individual developers would look at the second article and think that that's a lot of work for them, more work than they can justify, if they just want to improve their own work.

So while Joel would like you to not read the first article, I still think it is worth reading, especially for individuals. If you've got a manager who's willing to implement the ideas from the second article, great. If you don't have such a manager but want to improve your own workflow anyway, then I'd say the first is more relevant.

Karellen on August 5, 2008 9:33 AM

Well I just gave the link to one of my PM's and he said theres a problem. I've never read a book!!!

Why does it not suprise me!!! Does it come in audible version!?!?

Anthony Main on August 5, 2008 9:41 AM

Way to man-up and own the responsibility, Jeff! This was not only a good post in it's own right, but it was very humble and honest of you to respond to being called to task on your scheduling. Thanks for putting yourself out there.

Part of the problem I've had with making lists of what I need to do is the hubris of either "I *know* what needs to be done, I don't need a list" and the aforementioned "by the time I make the list I could be DONE with it!" But, honestly, there are some things I probably don't want to know that I have to do and writing them down in a list is not only acknowledging them, but is a form of committing to them :)

However, going from development to management to development again, I find myself WANTING a list of prioritized tasks. Partially because I want to know that what I'm working on is important (even the small stuff) and that my leadership (manager, VP, CEO, etc.) have all *THOUGHT* about what needs to be done, given a value to it and consciously decided what is more important than what.

That frees me up to not be worried about the stability of my job environment and to just code like a mad dog (...who's focused and directed and deliberately working on important things. Bad analogy, I know).

Anyway, excellent and thanks!

Tim Schmidt on August 5, 2008 9:53 AM

I really like The Art of Project Management by Scott Berkun (http://www.amazon.com/Project-Management-Theory-Practice-OReilly/dp/0596007868).

Peter Stuifzand on August 5, 2008 9:57 AM

A slaves work is never done -- Jam tomorrow, never today.

fxp on August 5, 2008 9:59 AM

Jeff, I was surprised to learn you were 37 (from the stack overflow site) -- many of the articles you write and things you say (here and the podcast) make you come across as a much (much!) younger, inexperienced developer. For example, "I'm almost pathologically bad about writing things down". How'd you get this far in the development world without being called out on that by your bosses?

dwj on August 5, 2008 10:10 AM

Scott Hanselman had a great podcast with one of the creators of Scrum on "what is the definition of done" for software.

http://www.hanselminutes.com/default.aspx?showID=137

Mark on August 5, 2008 10:14 AM

@dwj Obviously the wisdom that comes with age that you refer to doesn't include tact.

Marcus on August 5, 2008 10:18 AM

I have been once taught (by my former programming teacher; he worked for big software companies in Germany and Japan) the most essential truth about software development ever:

"You cannot estimate how long a programming task will take; period!"

I know that there are Mio of people who disagree, but I think this is absolutely true. Let me add some more quote

"Programming is not like building a house over and over again. If you build your first house, you have no idea how long it will take to build a wall, make the roof or creating one square meter of floor. Once you did all this, you know how long it took and when you build your second house, you know that it will take about as long as it did the first time, if not faster, since you are getting better at a task the more often you are doing it.
Every piece of code you write is a *new* piece of code, you are never repeating the same task again. Why would you repeat the same task? If you ever need the same code again, you copy&paste it; that will take you about 5 seconds. If you ever need the same application again, you just copy the one you wrote last time.
A software developer faces the problem that he needs to write new code every day, as there is no point in writing *old* code again. So every time the task is a new task for you. It's like you are building a house today, a car tomorrow, and creating a lovely garden the day after tomorrow; and you are always doing it for the first time. How can you estimate in advance how long you will need for it?"

This so very true! After years of development I can assure you, I'm doing something new every day. I'll continue to quote:

"Thinking you can estimate a task you have never done is just an illusion. You can make a vague guess, sometimes it's good, sometimes it's horrible. Sometimes you need twice the time and sometimes only half the time you estimated."

Actually all my time estimations are, well, I just make up these numbers. I have no basis for them. I could role a dice and the numbers would be as accurate as they are today. Quoting again:

"Programming is like art. Ask an artist how long his next painting will take. Do you guess you can get a reliably estimation? His picture is done, when he considers it done. He can't say in advance how long it will take. He might be 99% done and then consider some things need to be repainted and within a couple of minutes the state falls back from 99% to below 80%.
There will be the day where software developing companies are going to realize that. That's why OpenSource software is often better in aspects like performance or security; it's not time based. It's done when it's done. The developers themselves decide when it is called 1.0, not some marketing department or some supervisor. If they consider something a nasty hack, they'll fix it, even if this means it takes another 3 weeks for the software to be done."

As odd as this might sound, but I personally would prefer if the time frame is set from "above". I can surely make a list of all tasks to be done and show them to my supervisor every day; but I can't say how long each of these tasks will take.

It's a different situation if my supervisor says "Okay, for that, you have one day; for this one, it's very important, you may take up to three days; and for this tiny one, investing more than half a day won't pay off". If I know that I have only one day for this task and I start in the morning, I know it needs to be done before I call it a day. That means at the end of the day it's done. Whether it's good or not, whether *I* would consider it done or not, doesn't matter. It's done, because the time frame says it has to be done and if it's far from perfect, far from good, far from reliable... it's not my problem. The time frame dictates me when it has to be done.

If my supervisor then looks at the result and says "I'm not happy with it. This is too unstable, too slow, looks too much like a hack", I will reply "Well, you only gave me one day, that's the best I can come up with in one day. Give me more time and I will make it better". Then it's up to him to give me another day or maybe two days, to make it really good; or maybe not and it will stay as it is right now.

Mecki on August 5, 2008 10:36 AM

When you try and determine how long a project will take to complete, you must also factor in how long your analysis of how long the project will take to complete will take to complete.

I like id's approach... "When it's done."

Or if you're forced to make a projection, project high and look like a hero when it comes in early (or worst case, a good projector when it comes in on time).

Kris on August 5, 2008 10:44 AM

I must suk.

I'm a relatively jr developer (read poor architecture skills), working with a beta technology, with no real guidance. It's no wonder the project I'm on is taking forever. I mean i guess I kinda know what I'm supposed to be building.

Kinda.

I think I'm gonna sit down and make a list of all the stuff I at least know I gotta do. Then figure out how to do it.

Many times when someone asks how long something will take, I want to respond with "how should I know"? Mostly because in this ugly 3 years of a career i've had, I've never had a project manager or technical lead that had an idea what the architecture / end product is supposed to be.

When I pull a number out of thin air no-one calls me on it. It's a really bad on my part. Then again when I struggle there has never been anyone to help... so it's probably no wonder this project is failing and my last one did too.

Anyway thanks for this post. It reminds me that I don't want to suk and motivates me to be better.

brian on August 5, 2008 11:21 AM

Very nice post.

"It is the job of a good software project manager to recognize the tell-tale symptoms of this classic mistake and address them head on before they derail the project. How? By (forcing)encouraging developers to create a detailed list of everything they need to do."
I agree. My first thought, however, was to take "Tomas" up on his offer to "hand it off" as only "99-percent done". I don't know him well enough to know how well he normally estimates. (In fact, I couldn't know him very well given he'd been allowed to get into this situation.) But I do know that handing-off, or releasing, is the most effective way of shedding light on a situation. Once he has handed-off his "code", other eyes can be added to check for feature-completeness, and double-check his own residue list.

Further, rather than focusing on detailed lists (which is also necessary), I would restructure Tomas's work so that he is forced to hand-off, or at least demo, every day. Especially, as he moves forward to do his "cleanup", as these are all mini-features that should be independent and immediately obvious.

What I used to tell my students is to try and find a way to organize tasks so as to be able to show your manager some visible improvement every few hours (e.g., every half day) in case he or she walks into your office and asks how it's going. However, I told them that the main reason for organizing your work this way is for your own benefit. There's nothing like seeing new features (or new spec paragraphs, or help doc pages) every few hours that you can point to to build up your own morale (even if the boss doesn't walk in the door), and hence improve your own productivity. And it has the added benefit of getting you to think in terms of a list of things that you need to do.

Chuck S on August 5, 2008 11:27 AM

My best friend is MS onenote. Every time I think of something else that needs doing, I add it there with a checkbox. I've got all my projects organized nicely in one place. I also note all the steps I took during construction or bug fixing. This kind of organization and documentation is something I can't live w/o.

Brad on August 5, 2008 11:43 AM

Jeff,

I think you're missing an extremely important component, and thats to make sure that these list of items are all tangible things that can be verified as complete.

So instead of

Finish creating database tables

You have

Create User, Customer and Address tables according to spec 1.1 and select a demo record from each using Query Analyzer.

The difference is very subtle, but critical. Programmers(and I've been guilty of this too) tend to generalize things way to much. We end up with huge buckets like "Finish adding corporate logo to website". Well what does that mean? In all the headers? And footers? And that flash movie showing how cool we are? And the Apply Now page? And the Directions?

Its never clear when you're done. And if it isn't clear when a task is done, then it'll never be done, and always exist in that 99% finished state until someone just arbitrarily closes it.

Granted, you'll completely forget certain tasks, so they won't be in the original estimate, but thats how software managers grow and develop, they become better at breaking down the complex tasks involved in software development into those granular verifiable deliverables that can be tracked and benchmarked against.

WindyCityEagle on August 5, 2008 12:13 PM

I think programmers are inherently bad at time estimation of all computer tasks. Usually a programmer has in their head how they are going to solve a problem, fix a bugor what they have left to finish. This automatically put's it in your mind that it is an easy fix an will take no time at all.

One of the ones I find myself particularly bad at is report formatting such as in crystal reports. The reason for this is you find yourself going i will just move this then you test, then you add a field then you test I can find myself taking an hour formatting a report where in my head I have just said well just need to tidy up that report a bit make sure everything looks ok. Suppose this applies to most GUI stuff. This is one of the bits of the job I find tedious I usually fell I have done the bulk of the work and these are those last 10% jobs.

pete on August 5, 2008 12:27 PM

It's almost scary how often people seem to forget the fact that in order to know when you are done you need to know what being done means. There is no way you can say you are 83% done if you don't know what 100% done would be. That's like asking a contractor how long it takes to build a house without showing them any plans or drawings. Also, if you're not the only one working on the project, everyone else needs to know what 100% done means as well. The fact that the definition of being done tends to change during the duration of a project (new features, anyone?) doesn't help either.

I think this is one of the well-known problems of software development that Extreme Programming, Scrum and other agile methodologies and techniques are trying to solve. Even if they can't help you predict the future, at least they can help you see where you are, and hopefully where you are headed--or should be headed--in the near future.

Anders Sandvig on August 5, 2008 1:07 PM

Listing what is actually to be done, in detail, of course helps one plan better.

But I continue to be amazed, year after year, how managers think that writing down a list with times to completion actually makes it so.

I am likewise amazed that most managers don't understand the inherent lower-bound bias in initial time estimates.

John Pirie on August 5, 2008 1:31 PM

Jeff you are right about software project management books. EXTREMELY BORING almost all of them. I'll check this book out next time I'm at the bookstore.

o.s. on August 5, 2008 1:32 PM

> [Poppendieck's] article on team compensation (pdf) basically blew my mind; it forced me to rethink my entire perspective on being paid to work at a job.

The article was indeed an interesting read; thanks for the link. It does a good job of illustrating how a performance review system that forces managers to rank their team members, when the team members' performance was uniformly high, can cause problems.

However, the article seems to take that one case, and propose a set of performance review guidelines based on lessons learned from that single case.

What about, say, the case of a team that really does have one or two superior performers relative to the rest of the team; or the case of a team whose performance was mediocre across the board? Do the article's recommended guidelines apply equally well for managers of teams in those situations?

I would have liked to see the first portion of the article (which focused only on the high-performing team) also discuss the other possible cases.

Jon Schneider on August 5, 2008 1:44 PM

It's really a simple concept: if it's even possible for a task to be 90% done, then you haven't broken it down enough. Every task should either be "done" or "not done".

You can track elapsed time against estimated time, but that doesn't tell you how close you are to being done, only how close you are to a schedule slip.

Sadly, you're not the only one with this problem. Trying to get a work estimate out of some people is like pulling teeth.

Aaron G on August 5, 2008 2:00 PM

Some people at my company are perpetual "We are 99% done" people.

It seems after time and time and time again of being wrong, people would say to themselves "hmm, I seem to be overly confident a lot, I should think about that the next time I give an estimate."

Of course, they don't. They continue to try to please management (but really just frustrate them) by making estimates that are unrealistic and overconfident.

Never estimate based on the best case scenario.

TM on August 5, 2008 3:49 PM

Attempting to put software to a schedule is analogous to solving Turing's halting problem for a given input.

Sometimes you can tell very quickly how long something will take. Other times it is so nearly impossible to plan ahead that you might as well just start programming. Sometimes it's somewhere in the middle. Sometimes the schedule shifts midway from trivial to NP-Hard, or vice versa.

Realism on August 5, 2008 4:13 PM

Actually it's quite normal that there are more requirements/stuff to do then the team is able to finish before the deadline. SCRUM approach would be to ask client to prioritize the stories (tasks) and deliver those which are the most valuable. Projects are usually evolving, users ask for new features ... it's never 100% done from this perspective.

Marek Blotny on August 5, 2008 4:23 PM

How are you supposed to know what to write on the list?

The only way you can write a detailed list is to design the system. And designing the system should take about half the time in the project.

That's not to say that a list of tasks isn't useful, but getting to the point where you can write a list of concrete, completable development tasks may just be the biggest part of the project.

Steve Cooper on August 5, 2008 4:29 PM

I see really two threads to the responses here:
1. You're right and here's some more stuff on how to do lists and
2. I don't do lists, because it's too hard

I do think that there's some truth to the second, although I feel like a troll saying so. The problem is that a lot of time, when you're writing exploratory software, when you sit down to write up a list, you really, honestly don't know what needs to be done. And you can't flesh that list out to tasks that you can clearly say are done before you start doing some things. The "define the I/O behavior of module X" can't be drilled down, because it involves list items like "design the Y data model," and you don't yet know that you need a Y data structure.

I'm working on a project that's trying to use scrum now, and I'd have to say that while it seemed really agile in the beginning, it's now seeming like same old bad project management with generation of tons of tasks with ill-defined estimates for completion, etc. Precisely because we're doing tasks that need more work before they can be turned into lists of actionable items.

I'm starting to think that this is one of the software engineering dilemmas for which, as Fred Brooks said, there is no silver bullet.

Robert on August 5, 2008 5:06 PM

I don't understand why this is so difficult for most developers to do.

We're all so logical, right? Lists!

Jeremy on August 5, 2008 5:13 PM

Jeremy stacks are obviously most programmers favourite. You get paperwork dump it in a pile dump some more on top of it. I always tell my boss it's date ordered. :)

pete on August 5, 2008 5:42 PM

If you don't have a list, you never know when you are done or if you're late.

Most people don't update their schedule when they update their list.

Steve on August 5, 2008 8:09 PM

If I may make one suggestion....

First, Jeff..I loved your article about the quantity vs. quality and I think it applies here.

I'm a developer, like most people here, and I build a lot of software. However, unlike probably most of the developers commenting on this blog I have a team of ten people that I employ and I'm the head developer PLUS I'm the guy at the end of the day going "Criminee...I have $30,000 in payroll due tomorrow."

So the challenge for me has been how to do I get organized and sharpen my skills at the same time? I build software that keeps me organized!

I'll tell you what; build a to do list or two that meets how YOU like to work and it'll be worth it. As my skills and needs have changed, so has my to do list program. My program meets MY methods of organization and as those needs change so does the feature set.

Just a suggestion.

Jeremy on August 5, 2008 8:16 PM

I usually tell me team that if there's a but followed by the word "done" then its not complete!
I usually hear things like "its done but.. "

Shamelle

Shamelle @ TheEnhanceLife.com on August 5, 2008 8:18 PM

From what I have seen the "reward" cycle in IT has a number of problems:
1. The manager normally has no concept how subordinates do what they do, so are normally incapable of realistically measuring success. This is NORMAL in IT, because the manager is busy managing, not becoming a technical expert. So judgements on rewards almost always come down to perceptions and perceptions are almost never accurate.
2. Teams are more concerned about lack of performance by other members than they are about individually being singled out for praise.

In both situations a 360 degree process, where customers/clients/users, managers and team members all get to rate others. This way a manager may “love” a sycophant, but team members are able to report contribution and actual skill. Similarly, this gives the subordinates a chance to rate their leader. It is all done anonymously to avoid reprisal. In my experience this is the most accurate measure as it removes one person’s perceptions as the basis of assessment.

On the point of money, a couple of bonuses/raises in a row can become expected, so that a cycle of no raise can actually be seen as punishment.

Philip on August 5, 2008 9:50 PM

My rule is to make the most sober and pessimistic estimate you can and multiply it by two. Jeff, I'm sure you thought your initial estimate was realistic. If you had used the x2 rule you would have been dead on.

I did this once for a client I was working for. When I told him the estimate he said it was way too long and cut the estimate in half to what he felt was more realistic. Guess how long it took? :) Even when I'm right, I'm wrong.

I always work from lists when I'm trying to finish up a project. Once I feel like I've done all the major stuff I start listing all those annoying little fit and finish jobs in order to wrap it all up. The funny thing is that if I start with a list of 100 items by the time I've got 50 done I've accumulated 50 more. So even that estimate is crap. Yes boss, I did half the work, but I'm only 33% done. That's about when I start triage - next release for you and you, etc.

At least if it's on the punchlist it gets done (eventually).

Matt Lentzner on August 5, 2008 10:02 PM

Would somebody tell me how to estimate the time needed to debug?

Paulus on August 5, 2008 10:17 PM

I have had the pleasure of working with truly rubbish managers and directors. Men who have no idea about the development of software.

E.G.
Them - 'How long will it take to write this?'
Me - 'A year'
Them - 'Well I need it in 7 months'

What software producers don't realise is that it's a YEAR's worth of work - NOT 7 months. To deliver the product in the time they say do they pay for another programmer to assist in order to get the game finished on time?

No.

They expect you to suddenly double the number of working hours. Weekends gone, holidays - what holdays?

Sleeping on the office floor, being worked like a slave in a third world country and being driven to the point of absolute exaustion.

Development equipment that doesn't arrive until the project has started for two months...

I see way too much of this.

The life blood and creativity has been sucked out of the industry, programmers are no longer household names, just a number sleeping under a desk.

Does the book explain people skills, does it cover the fact that every day the programmer can't work because of lace of development kit the project should be extended by a day?

I could go on for a thousand pages detailing a litany of ignorance and bad management.


Simon Nicol on August 6, 2008 12:29 AM

How long will it take you to complete the Times crossword today?

What do you mean you don't know... I need an estimate... NOW!

Ok, so you're saying you want to look at the crossword first.. er ok.

Right now you've had a look at the questions, how long will it take you to answer the questions you don't know the answer to?

I need an estimate... NOW!! Its ok, I'll hold you to your guess later so if you're late, I'll blame you. I'll look good and organised and you can look crap at your job.

Simon Nicol on August 6, 2008 12:36 AM

Good programmers are like the hacker guys you see on TV.

Second 1: I've just broken through the pentagon firewall...
Second 3: (More keyboard rattling) ...now I'm linking from the pantagon through a NASA main server with 100 billion bit encryption... humm this is tough...

Second 4: Right I've just cracked the encryption and am bouncing the signal off a satellite now...

I honestly think directors/managers/producers are a thick as two short planks if they think this is how it works.

They can't program themselves because the're too stupid and they don't want to hear the truth about how long a program will take to write because they don't want to listen; anyway they always want it in half the time.


Simon Nicol on August 6, 2008 12:46 AM

tt

IVR on August 6, 2008 12:47 AM

Business opportunity:

I want to invest some money in software development. I've heard that huge amounts of money can be made if you get it right.

Here's 100,000. Now I expect to make a 50,000,000 in almost no time at all because I'm a greedy, short sighted, ignorant, git and the only thing I truly understand is how to screw people out of money - which is why I have so much.

To make sure the programmer I employ hit's my own arbitary deadline, I'll employ one programmer and five managers to flap around and piss about making notes.

Then I can take the programmer off working on the project and get him to write the schedules, work break downs, bar charts, pie charts and graphs that the managers should be doing.

THEN the five managers need to look like they have work to do so the only way they can do that is to constantly badger the programmer.

Does the book solve problems like this?

Simon Nicol on August 6, 2008 1:00 AM

I came up with a game design that was stolen by a BIG games company, the company I was working for at the time didn't see the potential of my design and so playing it safe they went for 'Die Hard 57 - OAP's revenge' (not the real name).

Am I arrogant in thinking my idea was much better than their 'safe' bet?

No.

Why? Because the game I designed went on (even though the idea was stolen) to become the world's biggest seller and the 'safe' game design though based on a very well known 'film' cost over 1,000,000 to develop and was a total flop.

The moral of the story: Let the designers and programmers design and program and the managers do what they're good at - Sweet FA.

Does the book have any suggestions on how to handle creative, intelligent people?

Simon Nicol on August 6, 2008 1:15 AM

I stopped reading that .pdf at "agile development".

Eva J. Culpepper on August 6, 2008 1:16 AM

It's all fun and games until you actually have to meet an estimate.

Programming is often like a bad RPG. You go to the castle just to find out the princess is in another castle. You go to the other castle to find it locked, but the key is held by the guardsman. You talk to the guardsman to find that he loaned the key to his son, who hasn't returned from the deep dungeon for a long time. You go to the dungeon and rescue the boy from the scary monster to find out he dropped the key on the way to the dungeon. You backtrack to find a note on the ground by someone who has taken the key back to the castle; the key is in the castle so you can't get in. You talk to the guardsman to find out another way into the castle, but it requires explosives. The explosives got stolen yesterday by a thief who lives in a cave by the lake. This thief would love to trade the explosives for these really wild barries that are located in the poisonous forest. In order to survive entering the forest you must first get magic syrum, which is gained by ....

I think you get the picture. The point is, you don't often know the real task list right away. This is especially true if you are integrating a familiar system with an unfamiliar one. If both systems are unfamiliar, the task may very well be impossible.

Skip this true experience of me using ANTLR if you're not interested:
I was excited to find a parser-generator to properly break up code for my project. I found out there was a book for it so I ordered it through Amazon. I begin by downloading ANTLR, which is archived. I find I have to update my java to properly extract it from the archive. All I need ANTLR to do is replace the function that breaks up code into a syntax tree. I download a grammar and run ANTLR using the example given. Instead of getting a tree, I get a flat tree of tokens (a linked list). I read about generating 2D syntax trees using rewrite rules; however, after trying to get the tree from one rule I find problems with the rules and ultimately decide this won't work. I search some more and find an example of an ANTLR parse tree which is generated from -debug mode. I find this to actually meet my needs, but I find that the parser puts every rule it tries to match (as opposed to the ones it actually does match) into its tree. This means I have to weed out duplicates, based on the start character and end character of the token. ANTLR looks like it has functionality to give you those values for all tokens; however, on parser tokens it will just return 0: you have to calculate the start and end of a parser token yourself (and put the parser token into a container with those values, as the set function for those values does nothing). Armed with all this, now I can properly integrate the ANTLR output. However, it is in a slightly different format now that it uses nodes instead of raw strings like before so I have to do some more work. What I had originally estimated for 1 month (including testing) is now 4 months into it and I am finally testing the last part of the integration.

ANTLR is a fine tool, but I felt like I was going through a bad RPG in order to use it. I can't think of a way to write an estimate that takes adventures like these into account.

AA on August 6, 2008 2:54 AM

We've been using the Scrum agile methods for about 5 months now.

Got to split up our work in tasks that are maximum a days worth. If you do fail to estimate the time a task will take, at worst you'll only be off a few hours.

Carra on August 6, 2008 3:46 AM


> Once you have all those items on a list

If only that was possible. The thing is that the list keeps changing. This is not necessarily a problem - that's what agile techniques are for.

The real problem is thinking there is such a thing as an accurate estimate for a big software project.

IME the best you can do is estimate user stories or use cases in story points (**not** days - programmers are notoriously bad at estimating time), track your velocity in terms of story points/day, and predict from that how long to do all the things that are currently in your list. If you haven't already, look up burndown charts.

The whole issue of what "done" means for a task needs to be addressed too. Too often programmers think it's just delivering code, and don't consider testing, code reviews, documentation etc

Jim Cooper on August 6, 2008 3:56 AM

> Would somebody tell me how to estimate the time needed to debug?

You don't. Debugging should be a part of the construction/programming activity. Unit tests and continuous integration will help you on the way, but if the task takes longer than expected--because you spend a lot of time debugging--chances are the task is more complicated than you first estimated, or you chose the wrong implementation or design approach. Either way, you should re-estimate the task or break it down into new, smaller tasks and estimate them instead.

Anders Sandvig on August 6, 2008 5:35 AM

I am never able to understand why this percentage completion comes into place. I worked for Nationwide Insurance, for 7 months. And those guys keep on asking how much percentage you have done. Obviously, I was never able to answer it. I mean, how can I tell that this home page that I am designing is 50% done, when I have just started coding. Software development is not like baking a cookie, in which you can precisely tell how much more time it will take to bake it up in your microwave.

jitendra garg on August 6, 2008 6:04 AM

In Scrum (mentioned by a few others), the list of things to do is called the backlog, and it works wonders. I work in a development center where all projects use scrum, and it's working very well for us.

Jeroen on August 6, 2008 7:24 AM

I guess, it's a developers desease not to plan ahead, cause "it takes the time that it takes" and we don't like to feel pressurised to complete the work we've commited on. ;)

@jitendra
Actually, you can give a percentage estimation! Not precisly, though... In the company I work for, we use SCRUM now for nearly 10 month - and besides some teething troubles, it serves us great. We're forced to think of the tasks a user stories needs to be completed (that is, the code is tested, documented, possibly reviewed and demonstrated). Taks are estimated in hours, considering possible know-how-transfer and pair-programming. If a tasks takes longer than 16 hours on the first estimation, it has to be broken down in smaller pieces where applicable. We tried to use story points for estimating the user story, but gave it up in favor of "ideal man days". (We found it really hard to measure complexity, work load etc across 3 teams with different scopes).

Since using those agile methods, seeing the tasks on our board and checking on them daily, we have massivly increased our effectiveness!

Barbara on August 6, 2008 7:26 AM

@AA

I like the analogy - entertaining and pretty accurate.

HB on August 6, 2008 7:47 AM

The challenge with making a complete list is that you can't anticipiate everything and it takes too much time anyway. It's waterfall as someone else pointed out.
In agile methods you tend to have a backlog. The key is NOT to list ALL the tasks at the beginning.
Requirements basically come in course grain requirements (CGRs), which are broken down into fine grain requirements (FGRs) which are broken down into tasks. CGRs can typically be completed in a couple of weeks, FGRs in days and tasks in hours (may vary by project and temperament).

Now, at the beginning of the project it is relatively simple to list all your CGRs, it shouldn't be too long a list.
You then take about 10% of your CGRs and go to town on breaking them right down into FGRs and tasks and then you estimate it all carefully. Yes, this will probably take a few days to do but it is worth it.
This will normally allow you to estimate the remaining 90% of CGRs reasonably accurately without actually doing the detailed break down.

This allows you to do the detail break down of each CGR later, when you are just about to start the work. Just in time estimation :)

The most important tool we use is the burndown chart and the run-rate.
So, if you estimate all your work and then measure how much work you actually get done then you can apply your "run rate" to make your remaining schedule much more accurate. For example, if it consistently takes you 60 hours to do what you estimated to take 40 hours, then you can apply that formula. We do that with our development teams and it means we get fairly realistic delivery timescales over time. But, this only works once you build up a history of data, of course.

In addition, the burndown gives you a constantly updated estimate of the release date as well, driven by developers without a project management overhead.

If all the above sounds like theory - well, it's how we work with our onshore and offshore delivery team. It is not without problems but it beats any other method I have ever used in terms of transparency and accuracy.


Frans Lytzen on August 6, 2008 8:45 AM

I like software project management books.Its really awesome

Hostmonster on August 6, 2008 10:44 AM

For the social science of management I like, "One minute manager", "Becoming a technical leader" by Weinberg, <a href="http://www.druckerinstitute.com/">Drucker</a> and <a href="http://deming.org/">Deming</a>. For the technical, how about a six-sigma approach.

At the end of <a href="http://www.artima.com/weblogs/viewpost.jsp?thread=235983">Bruce Eckel's</a> blog entry, he mentions what the answer might be for successful, innovative development. Similar train of thought as <a href="http://en.wikipedia.org/wiki/The_Mythical_Man-Month">Mythical Man-Month</a>. EDS for awhile had an interesting take on projects. Which is similar to the Eric Raymond reference in Eckels blog entry. Teams are mobile w/in an organization, and individuals within teams are mobile.

dj on August 6, 2008 4:27 PM

Bravo!

In my recent experiences at startups in silicon valley it is entirely too common that development teams only receive verbal requirements and at best, confusing direction. Product managers and development leads, and decision makers simply must take appropriate time to clarify the desired product and its features (and actually write them down coherently rather than in sound bites).

Developers and especially offshore teams must have the ability to contemplate requirements in written form as a "stake in the ground" upon which to ask questions and at least have a starting point to establish reasonable expectations.

Or I could be living in a dreamland.

Nick Waters on August 6, 2008 10:57 PM

Doh. I missed the point before I hit Post.

Taking time to capture remaining work and measuring against completed tasks allows for more precise time estimates, and raises the integrity of the developer. This completes the loop on the project management.

P.S. With all due respect to "agile" methods, it is perverted by those who claim that "the code is the documentation." Those who say such things are, in my opinion, too lazy to document at least the APIs between major areas of interacting code which multiple developers are working on together.

Nick Waters on August 6, 2008 11:03 PM

Do you think Open Source manages development better or just differently? I'm always amazed at kernel, system, and application development in Linux.

"The Cathedral and the Bazaar" by Eric S. Raymond
http://en.wikipedia.org/wiki/The_Cathedral_and_the_Bazaar

dj on August 6, 2008 11:34 PM

Hey Jeff GREAT POST
Usually I come here for a laugh and to challenge my ideas because you are well sometimes (mostly) a bit off the track but this one is different one of the rarities
keep your opinions opinionating!

amused on August 7, 2008 6:01 AM

About this time you begin to realise that no matter what you say (Jeff that is) or have said, most of the responses are from people that cannot read or cannot comprehend, no matter what. How very depressing. But still, lively debate, as they say, can only improve our understanding of the human condition. Keep up the good work!

amused on August 7, 2008 6:26 AM

Try some English humour (apologies for the correct spelling!)

The Mighty Boosh on August 7, 2008 6:31 AM

I guess I'd catagorize this as a nice try, but I don't see *anything* that can get rid of the month-long 90%.

I'll give you a current example. I'm working on porting some code, and after a *lot* of fits and starts, have all of it working except the byte swapping on some of the variables transmitted to another machine is wrong. How long of a task does that sound?

Well, it turns out after a 3-day investiagtion into the old code, that the code my predecessor on this project wrote to handle parsing of the executable's debugger STABS isn't picking up the FLOATs for some reason. They were all comming out as INTs. How long of a task does it sound now?

Well, it turns out, after another week and a half dive through the 10KSLOC that parse STABS, that all 10KLOC are doing exactly *nothing*. I can comment it out at the top and the program works exactly the same. Its pretty clear to me that its going to be easier to write the STABS parsing code over myself rather than try to get a totally nonfunctional 10KSLOC routine working the way I need it to. I've written parsers before. Wrote my master's thesis on it actually. And I have all this old code that at least shows me what the proper calls to make are. So how long of a task does it sound now?

Well, it turns out that, outside of the creators of gdb, almost nobody ever has to write a parser for STABS. There's only one piece of documentation I can find anywhere. It also turns out that the format is really contorted, and is totally designed around the implementation that the linker (and in some case gdb) writers happened to be using way back when. Still, after a week I have it working for some basic types. In another week, I have it working for the complicated types too. The only remaining issue is that it isn't quite handling some of the C includes and Fortran scopes right. So how long of a task does it sound now?

Well, it turns out that Fortran's scoping rules are different than C's, and rather than encode that difference in STABS, they figured they'd let the parsers handle it. So now I have to go back and recognize what language each object file was coded in and handle the parser's scopes totally different for different languages. There goes 4 days.

It also turns out that they decided to economize on file size by not spitting out the entire contents of identical includes. Instead they just referenced them by name and a hash key. After a couple more days I figure out that you need the hash key because #ifdefs can make the same include file really a different file in different compilations. They still cheated a bit on this in the cases where some include files in include files aren't reincluded. Tack on another 2 weeks to deal with this.

If you have some estimating method that can prevent this rather typical example of the perpetual 90%, then in my book you are now only 2 miracles shy of your sainthood qualification.

T.E.D. on August 7, 2008 6:36 AM

That's kind of long. Sorry.

I guess what I'm really getting at is that a lot of the time estimating on a software task before you actually start working on it is like estimating how many dolls are in a matryoshka doll without lifting any of them. You can try to eyeball it, but really its just going to be a guess. Often a horribly wrong one.

T.E.D. on August 7, 2008 7:12 AM

Thanks for this article! To-do lists are everyone's best friend, and it's great to see you advocating them.

Josh M on August 7, 2008 8:57 AM

@Andrew Peters: Amen! A 30 day sprint where you are supposed to execute exactly what's been perfectly planned out in advance in a requirements document isn't agile and certainly isn't iterative, even if you have scrum meetings every morning.

I keep a personal list of issues that I discover need to be worked on, and I've found it's useful to keep this separate from any bug tracking, sprint backlog, or other team/manager-owned artifacts. Sometimes items from the personal list translate into new issues or revised estimates to bring up with the team, but often they are details that just get resolved in the course of work, the important thing is that you have a way to capture issues as they arise so can figure out what you need to do later. This is very loosely based ideas in David Allen's _Getting Things Done_.

Marc on August 7, 2008 10:29 AM

I knew a guy who said that the proper way to estimate time needed to finish a programming job was to take the time you think you will need, double it and move it up to the next time level, that is, 5 minutes is ten hours, 2 hours is four days, and three days is 6 weeks...

Terry Smith on August 7, 2008 12:43 PM

Lie, sometimes.

Predictability is better than speed. In a perfect world you'd be able to honestly communicate that you're done early, or that xyz happened, or just that it was a lot harder than anticipated, and people would understand.

So then we want to overestimate, and give a 'worst case' deadline. We're honest and quite proud that we're done early and tell everyone. The problem is that if you do that too often, then there's an expectation that you're always done early. If your estimates get better, it doesn't matter, because people expect you to be early.

So, you lie. You pessimistically estimate 3 weeks, and if you're done in 1, or 2.5 hours, it doesn't matter. Just test the code more and read Dilbert. When the deadline approaches, announce you're done just a shade before the estimate. Try to estimate better the next time around.

In the end, you'll be known as the guy who always delivers on time. Your schedules are predictable, and everyone is happy, including you, because you have less stress in your life. Predictability also helps your manager, because he trusts your estimates, which allows him to be confident talking to his bosses because his timelines are better too.

frist on August 7, 2008 2:29 PM

> So, you lie. You pessimistically estimate 3 weeks, and if you're
> done in 1, or 2.5 hours, it doesn't matter. ... Try to estimate
> better the next time around.

You seem to be buying into the myth that your "estimate" can *possibly* be anything better than a SWAG. What's worse, you seem to be beating yourself up over not doing it better somehow. Forgive yourself for not being clairvoyant, give your guesses, and move on.

T.E.D. on August 8, 2008 6:13 AM

I thought the caller in Podcast #16 was a bit harsh really. It sounds like Jeff has done a good job so far getting out a beta quickly and getting early feedback.

I've realised I've falled into the 90% trap myself. I've blogged about it here:

http://confessionsofasoftwaredeveloper.blogspot.com/2008/08/always-being-90-done.html

Planning seems such an obvious thing, but as a programmer it's too easy to get caught up in features.

C.O.A.S.D. on August 8, 2008 6:26 AM

Quite often the situation I find is we cannot list down the things that need to be done at the minute level. If that happens, that means we have the design completely laid out in the clear, without having to *think* a single bit during the construction phase.

Have you ever found yourself in such a state? Knowing exactly when you will be done with a task/feature, by the hour? I have never.

I try to accomplish a task according to a rough plan, because I have _never_ done it before, so I can only follow a broad educated-guess approach. And then an error occurs, or unexpected behaviour or results are returned; dig around, step and debug, search the Internet or newsgroups for discussions or articles on said topic, post a question, wait for answer. Works on this machine, not the other. Make configuration inspections and tweaks. Guess what? two or four days have past.

Was that factored in? nope. Most of the time, the "buffer" schedule is never enough to cover for these hundreds, if not thousands, of small little and big issues popping up here and there and stalling developers.

Aaron Seet on August 8, 2008 7:13 AM

It is a bit pretentious to consider a blog-project as a measure for project management on any software development project. Also, Jeff's project looks a lot like a digg web site (or any web site with "digg" functionality). True challenge on every software development project are the requirements, integration, configuration and (smooth) rollout. By large, the biggest amount of time in software development process is eaten up by requirements and the back-and-forth between business sponsors and middle management. Coding is usually done in whatever time is left after that, with more requirements changes along the way.

If your software development is slipping even though you had detailed requirements, you need to "update" your team. Senior and middle management also need to update their technical skills, to fully understand the implications of each technology used.

BugFree on August 8, 2008 11:02 AM

In the olden days (Windows 286) I worked at a place where we did fixed price work. The design doc was a paid deliverable, then we had to estimate the # of hours per screen, etc.

There was a precursor to MS Project, a DOS app called "Timeline", that was in some was quite superior. I tracked the burn rate and physical completion % of each piece.

It was (and is) doable. But in today's world it isn't the norm to think things through perhaps? And, when our client wanted a change it was always "time and money" -- but maybe we don't hold our clients accountable as often as we should?

If there is no completed spec then you can never be done, and there is no delivery date that really can be promised.

Steve on August 8, 2008 4:00 PM

Yeah, I feel the same pain always. Well, I admit that it may be the developer's fault in that he/she may overestimate his/her own capability. However, it is not unusual that even you have a clean plan at the beginning, feature request/changes from the customer quickly suck your buffer time quite easily. Sure, you can allocate twice or three times more time to prevent it from happening. Then, you will find that you lose the customer as somebody else may claim that they can do it in a much shorted time. What do you say? Perhaps, that is the reason why Ruby on Rails becomes so popular.

James Kuoski on August 9, 2008 7:14 AM

Speaking from experience, for a long time i stayed away from making Task Lists to organise my time.

It wasn't until i forced myself to use them for a particular project that i realised how damn useful they were. My productivity improved and i really felt like i was getting something done (since i could actually see it on the screen) - as opposed to being clueless and taking much longer to get anything done.

I Just wish that i would have figured that out sooner. :)

James Urquhart on August 9, 2008 8:23 AM

"The advantage of Software as a Service is that a 90% complete solution can often be put live with the last 10% being "mopped up" as required."

That creates a pretty useful standard for 90% done... if a developer says something is 90% done, you can ask the question "if you had to ship it, could you?". If the answer is "yes", perhaps it really is 90% done, with a fair amount of cleanup work left. If the answer is "no", then you aren't 90% done. If the core functionality isn't there or it flat out doesn't work, you aren't really 90% done.

Of course, this is one area where test-driven development helps a ton - you know exactly what the target is (documented via the tests) and you know exactly when you meet the target (tests pass). Makes the line between "done" and "not done" far clearly.

coderprof on August 9, 2008 6:01 PM

>>>This software developer does not have a detailed list of all the >>>things he needs to do. Which means, despite adamantly claiming >>that he is 99 percent done -- he has no idea how long development >>will take! There's simply no factual basis for any of his schedule >>claims

First off, knowing that you are 100% done is relative. Are you talking about 100% meeting the functionality for the business requirements or do you mean that -plus- time added for unit testing AND some sort of initial cleanup? Be clear when you ask that question to your developers and don't pressure them to give you the perfect answer you expect because you just want to get your CIO off your back.

Now I'm not advocating letting your developers give you a grey answer every time, I'm just saying listen to your developers, don't always expect 100% perfect estimates. It's your job to build in cushion for testing and also I feel some for cleanup and you should be direct with the business that the standard is this and push back a little when the business is telling you to skip that part of the project and that this is not important.

I think this cleanup portion (aside of just functional code for the business requirements checklist) is very interesting (sarcastically).

Often times your manager doesn't give a damn about the cleanup you talk about when he asks you how much you have done for a,b, and c in the project plan, and just wants the stuff out the door because they are pressured. If you tell him or her well, it's "functional", quite often, they're gonna tell the all too common "you ah that's good enough", "don't clean anything up right now", "we are not looking for perfection", so lets just get it to QA. To me that's piss poor management. The developer is also not looking for perfection. He has a life and he just wants to do a little cleanup usually so chill...give some time for that.

There should always be a -short- period of time built into your project plan (1-2 SOLID days or so) for cleanup by your developers in addition to time for GOOD unit testing. Being 100% accurate about if you are done is relative but at the same token, you can't skim quality just because you want to force them to give you a hack job and say it's 100% and functional even though it has not been tested well, and there are some important cleanup that would affect the team or the application which affects the business later down the road which you know probably will never be refactored due to lack of time which resides in most IT shops dictated by poor management and unrealistic business timelines / expectations.

I think not polishing some of your code before it goes to QA is code and run and just a half assed approach to development and management no matter how much the business is breathing down your back. If your developer does not feel comfortable pushing it to QA, step back, let him have a day or two more to do some of that testing or cleanup so that he can feel confident that the application is fairly solid and so will you because you "trust" your developers. Maybe they had a long night (wife got into a car accident night before) and they really need that extra day to clean up. Think about the human aspect of that also as you address your developers, not just the business needs every damn time.

Dave Schinkel on August 9, 2008 10:18 PM

Forcing works better than encouraging.

Silvercode on August 9, 2008 10:52 PM

As a project manager, I found this highly entertaining. If you're going to have to "effectively do project management", you may have to learn some principles of project management, even if you are normally a programmer. In my organization we are lucky enough to have people like myself who can spend their time breaking tasks into WBSs and such, which give you much better estimates for completion. Once you have these tools, when you are monitoring a project you can ask better questions than "What % done are you?", instead you ask questions like "Which of these tasks are complete?", then you can go back and really figure out how much more time to complete the project.

Personally I've found percent complete is misleading, I'd rather know how much I've spent, how much I've earned, and what its going to cost to complete.

Scott on August 12, 2008 9:53 AM

If the source code is written decently, I find that the biggest factor is the developer's perception of what "done" is. So, I always ask if their estimate includes issue mitigation. Many times it does not.

Then, I ask them how many cycles of mitigation the change will take (usually based on complexity of the changes or the developer's knowledge of the code). From this conversation, the developer almost always adjusts their estimate of completion. Over time, the developer just gets better at estimating since we are always asking pretty much the same set of questions.

Areas that need refactoring are typically the worse for trusting anyone's estimate for any changes. I try to factor this in when setting expectations with the customer.

Kuch on August 12, 2008 3:39 PM

Horay! Jeff has discovered Agile!
Just few more years and object-oriented programming might follow...

The Sloth on August 12, 2008 5:39 PM

>>>Forcing works better than encouraging.

Now, that is just a stupid statement altogether.

Dave Schinkel on August 13, 2008 6:29 PM

To any one who doubts whether this from the Poppendeick article is real, it absolutely is:

"The Aftershocks - Two days later, Sue got a call from Janice in human resources. “Sue,” she said, “great job your team did! And thanks for filling out those appraisal input forms. But really, you can’t give everyone a top rating. Your average rating should be ‘meets expectations.’ You can only have one or two people who ‘far exceeded expectations.’ Oh, and by the way, since you didn’t rank the team members, would you please plan on coming to our ranking meeting next week? We are going to need your input on that. After all, at this company we pay for performance, and we need to evaluate everyone carefully so that our fairness cannot be questioned.”"

That's exactly the way it was done at the last company I worked for, except as a team leader you probably weren't going to be fortunate (or unfortunate) enough to be invited to the meeting where they change all your scores for you. They called this the "normalizing" process; a nice bell shaped curve keeps the bonus amounts down. Of course, no one was told they'd be screwed like this when the company dangled the bonus out there in order to get people to accept lower starting compensation.

*Never* put any stock in the promise of bonuses; *always* assume that the salary you are offered is the only monetary compensation you'll ever see. In 15 years of doing this, I've yet to see a decent bonus. There's *always* been a reason not to pay them out in any meaningful amounts (slow economy, projects went under budget, we grew so much the profits were too low, etc.).

anon on August 14, 2008 11:46 AM

I couldn't disagree with this article more! I have responded to this post on my blog:

http://blog.robbowley.net/2008/8/11/lists

rob on August 16, 2008 5:51 AM

We are already living in the matrix, so there's no telling what is real even as you walk down the street :)

Craig Lebowitz on August 22, 2008 1:57 PM

Some painters spend years perfecting their technique.

On the other hand, one particular painter I saw on TV just picks up a bucket of paint and throws it into the airflow of a Jet engine and the paint gets randomly splashed on to the canvas.

How long did it take to paint the Cisteine Chapel? And how long does it take to throw a bucket of paint in the air?

Michael Angelo's masterpiece took over 4 years to complete - Can you imagine ANY manager being happy with that?

The American painter who throws his bucket of paint in the air spent just under 30 seconds on his master piece and it sold for over $1M. Is this man over 4,204,800 times better at painting than Michael Angelo?

Which one is more famous?

There are no short cuts to quality.

If you want perfection it takes more than 5 minutes. If you want shit, don't ask a creative genius to sacrifice himself on the altar of your greed.

You only get out what you put in. The Universe works this way - No amount of management and pissing about will make the process any faster, only smoother, by making sure the 'creatives' have all the tools they need.

The only question a manager/producer/director knows or cares about is "HOW MUCH MONEY CAN I MAKE AND HOW QUICKLY CAN I MAKE IT?"

As soon as you all admit that, then management and creative people will have a better understanding.


How long will it take? TWO WEEKS - lol


Sci-Fi Si on November 3, 2008 1:20 PM

In response to: "Until you've got at least the beginnings of a task list, any concept of scheduling is utter fantasy. A very pleasant fantasy, to be sure, but the real world can be extremely unforgiving to such dreams."

Your statement is misleading. It implies there is a state where schedules are in fact not utter fantasy.

I do agree it is critical to write all these little things down. But they are not required to make a schedule. Schedules have varying degrees of precision, this technique can improve the precision of your schedule. (make it less utterous)

There is a folly though to think you should do this breakdown for every task on the schedule, up until the end date. You're understanding of what you need to do 3 weeks from now is vastly less than your understanding of what you need to do today. Creating a very granular breakdown of something you're doing in 3 months is potentially a useful exercise but it will not increase the accuracy of your schedule.

fschwiet on December 30, 2008 5:58 PM